Distributed Energy Scores Big Win in US Wholesale Markets with FERC Order 2222

Sept. 18, 2020
In a big win for distributed energy resources, FERC approves Order 2222, paving the way for aggregated DERs to compete alongside traditional power plants in wholesale markets.

The Federal Energy Regulatory Commission (FERC) on Thursday issued Order 2222, its much anticipated ruling that paves the way for aggregated distributed energy resources (DERs) to compete alongside traditional power plants and other grid resources in wholesale markets.

The landmark ruling was heralded in a commission news release as important to “help usher in the electric grid of the future” by removing “the barriers preventing distributed energy resources from competing on a level playing field in the organized capacity, energy and ancillary services markets run by regional grid operators.”

Previous FERC rulings have opened wholesale markets to distributed energy resources in general, but Order 2222 will now enable these resources to be bundled together into a single bidding entity, opening new possibilities and competitive opportunities.

What’s included in FERC Order 2222

FERC’s expansive ruling opens the door to a wide array of technologies to participate. Aggregate resources can be located on a utility’s distribution system (or a subsystem) or on-site behind a customer’s meter. 

Bundled technologies can include energy storage, on-site renewables, energy efficiency, distributed and backup generators, electric vehicles and their charging equipment, and other energy systems common in microgrids. There is no practical limitation on the number of distributed technologies that can be networked together in this manner, and combinations of generation and load modulation can be deployed simultaneously into one unified market offering.

Most notably, this new rule allows several distributed resources to aggregate to satisfy minimum size and performance requirements that they might not be able to attain individually, meaning aggregation can open access to any and all DERs located in competitive markets.

What happens next

The basis for FERC Order 2222 stems from the commission’s court-affirmed jurisdiction under Order 841 to regulate regional markets and any necessary participation criteria. FERC has now asserted that it wants aggregated resources to participate, so each regional grid operator must revise their tariffs and participation rules to accommodate this dynamic class of resource.

The order will officially take effect 90 days after publishing, and grid operators must then make compliance filings to the commission within 270 days of the order going into effect. Compliance plans are therefore due in about a year. They must  propose a pathway for participation that is customized to each market’s needs and outlines their timely implementation of the order.

Bundled technologies can include energy storage, on-site renewables, energy efficiency, distributed and backup generators, electric vehicles and their charging equipment, and other energy systems common in microgrids.

In announcing the final ruling, FERC made clear that aggregate resources will be able to “register their resources under one or more participation models that accommodate(s) the physical and operational characteristics of those resources,” restructuring capacity, energy and ancillary services markets run by regional grid operators.

Under these auspices, FERC has laid out minimum requirements for each market to conform to when setting up their participation models. They include:

  • Adhering to minimum size requirement no larger than 100 kW
  • Addressing technical considerations like locational value and distribution factors
  • Incorporating advanced metering, telemetry, and data requirements, among other provisions

Order 2222 upholds previous determinations that allow resources connected to the distribution grid to serve both retail and wholesale markets, but also directs grid operators to include “narrowly designed restrictions” necessary to prevent double counting of services. 

This order does not supersede previous rulings that allow local utilities to prevent customers from bidding local demand response into regional markets, and it will still allow some of the smallest utilities (<4 million MWh) to opt their customers out all together.

Local utilities will also still maintain jurisdiction over interconnection of distributed resources to the electric grid, whether or not the resource intends to participate in retail activities. These types of local utility considerations will help prevent legal challenges that bogged down previous proceedings on demand response and energy storage.

Celebration abounds

The long-anticipated decision elicited positive reviews from industry leaders and recognition of FERC Chair Neil Chatterjee and Commissioner Richard Glick for their leadership.

“Today is another landmark day for competition and innovation in the power sector,” said Energy Storage Association CEO Kelly Speakes-Bachman in a statement, adding that the order “removes regulatory barriers to aggregation of distributed resources in wholesale electricity markets, and is the next step forward for energy storage and other distributed energy resources.”

Update: Check out the latest news on the distributed energy resources market.

Others noted that with so many nascent types of DERs emerging on the grid, that for many of them policy and regulation is ahead of technology, an uncommon situation.

“The draft rule is a big win. It provides an overarching framework for DERs to participate in wholesale markets,” said Ravi Manghani, Wood Mackenzie’s head of solar. “Policy is leading technology for the first time, at least as it pertains to emerging DERs like vehicle-to-grid.”

A multi-billion dollar opportunity awaits

The different regional wholesale markets oversee hundreds of millions of dollars in energy transactions every day, and FERC’s ruling will open the door for DERs to access those competitive opportunities.

Previous FERC orders allowing for grid-tied energy storage systems to access limited market opportunities (like frequency response) caused a bit of a battery gold rush in early mover markets like the PJM Interconnection. New wholesale revenue opportunities combined with declining costs and increasing retail value could spur new deployments and accelerate the already burgeoning DER sector.

While the specifics of each market’s implementation plans are still months away, FERC Order 2222 is a major win for the DER industry and will have a significant impact on how distributed resources are designed, operated, and compensated for years to come.

The FERC order is available here.

Matt Roberts is the director of strategic growth & government affairs at Microgrid Knowledge.

Track news about distributed energy resources. Subscribe to the free Microgrid Knowledge Newsletter.

About the Author

Matt Roberts

gettyimages1341067688_sdl__1320x755

Revolutionizing Defense: The Crucial Role of Microgrids and Schneider Electric in Department of Defense Energy Resiliency

Sept. 13, 2024
Last month, the North American Electric Reliability Corporation (NERC) said that U.S. power grids are becoming more susceptible to cyberattacks every day, with vulnerable attack...

MGK_MesaWPCover_2021-09-07_8-14-03

6 Reasons Why Natural Gas is a Distributed Energy Source Bridging Solution

Many experts predict a windfall for the renewable energy industry as companies strive to meet their stated goals by 2035, 2040, or even 2050. But a new white paper from Mesa Solutions...