Exploring Detail Engineering Challenges in Microgrid Implementations

July 17, 2017
Microgrids offer a number of interesting and valuable capabilities to their owners, operators, and customers. But there are a variety of detail engineering challenges that can arise in microgrid implementations. The team at POWER Engineers explores some of the most common challenges and how to overcome them.

In this week’s Industry Perspectives, the team at POWER Engineers explores common detail engineering challenges in microgrid implementations and how to overcome them. 

Microgrids offer a number of interesting and valuable capabilities to their owners, operators and customers. Increased impact of renewable sources, increased electric reliability, and increased resiliency are just a few of the positive attributes microgrids bring. Among the most critical performance issues are the following:

  • Voltage and frequency stability: Does the microgrid include the correct mix of real and reactive power sources and sinks to generate and deliver energy with necessary stability? How fast must non-critical loads be shed to maintain stability when unintentional islanding occurs or when an in-grid source is lost?
  • Protective relaying performance: How fast must faults be cleared from the islander microgrid to prevent loss or microgrid collapse? How quickly do voltage and frequency recover after successful fault clearing? How do topology changes impact fault detection and protective device coordination?
  • Ground source arrangement: Where are the microgrid ground sources? Are they available during islander operation
  • Arc flash hazards: How are they different in islanded operation and what can be done to mitigate increased flash hazards.

The challenges above are exacerbated when constraints such as project cost, original system electrical topology, and available physical space seem to limit placement options for microgrid apparatus in new or existing systems. An upcoming paper and Microgrid 2017 Conference presentation by John Kumm, director of SCADA and analytical Services at POWER Engineers, will explore the topics above in detail.

The challenges above are exacerbated when constraints such as project cost, original system electrical topology, and available physical space seem to limit placement options for microgrid apparatus in new or existing systems.

John Kumm, POWER Engineers

A typical microgrid topology

Figure 1 below presents the representative topology of a microgrid the authors contributed to. In this case, the original microgrid designers met cost and physical constraints by connecting a traditional critical power Genset Bus to the Main Bus and to the Critical Load Bus. The Main Bus connection supports microgrid operation. The connection to the Critical Load Bus is through an Automatic Transfer Switch (ATS) which provides more traditional functionality for critical backup power. Other microgrid elements, including a Battery Energy Storage System (BESS), a small combined heat and power (CHP) unit, and a solar photovoltaic (PV) array, were each connected to physically nearby buses as cost containment. While the design met economic and physical constraints, the topology yielded several performance challenges:

  • Fault current sources, magnitudes, and pathways through the system are dramatically different under islanded versus parallel operation.
  • Traditional time-overcurrent protection elements employed take longer to clear faults that occur during islanded operation, so fault clearing times vary widely depending on whether the microgrid is islanded or parallel.
  • Stable fault ride-through for utility faults near the microgrid or normally-cleared, non-generator faults within the microgrid depends on the complex interplay between:
    • Fault clearing time
    • Generator inertia and initial loading,
    • Synchronous generator excitation response, and
    • Load response to both fault application and clearance.
  • Arc flash hazards, present for workers near energized apparatus, depend on fault current and fault clearing time, among other factors that are not variable for a given system. Flash hazards will depend on whether the microgrid is islander or parallel and each viable topology should be reviewed to identify worst case flash hazards.

Figure 1: A Typical Microgrid Topology. Courtesy of Power Engineers

Resolving typical microgrid topology challenges

When a microgrid must be implemented using a similar topology to that shown in Figure 1, consider the following analyses.

When possible, use differential or communication-aided protection to improve fault sensitivity and decrease tripping delays. This may increase equipment cost but offers the benefits of faster fault clearing, more stable microgrid operation, and reduced arc flash hazards.

When coordinating time-overcurrent protection devices, identify all ground sources, generation sources, and coordination paths from to the fault. Protective devices close to the fault will often see the largest fault current. Be aware that CT ratios and current pickup sensitivities both influence device tripping speed. Coordination that works in one topology may not work when sources are added or subtracted.

You may wish to install transformer neutral grounding switches that selectively insert or remove microgrid ground current sources, depending on microgrid topology. If microgrid slanging removes the only microgrid ground source, this is required for effective grounding at the point of interconnect voltage level.

After protection coordination is complete, analyze arc flash hazards for all foreseeable microgrid topologies. Develop a plan to keep electrical workers safe and informed regarding the hazards for different topologies. Consider arc detecting relays for indoor or metalclad switchgear. These can speed clearance of arcing faults and reduce arc flash hazards. Carefully analyze arc flash maintenance modes. We have found that accelerated overcorrect tripping does not always yield reduced flash hazards due to fixed breaker operating times.

[clickToTweet tweet=”Analyze arc flash hazards for all foreseeable #microgrid topologies.” quote=”Analyze arc flash hazards for all foreseeable #microgrid topologies.”]

Standardized topology reduces engineering cost, complexity

We are looking forward to November when we can share more technical details regarding the topics above and a standardized and modular microgrid topology. This topology can be employed to both improve microgrid performance and reduce engineering costs. See us in Boston November 6-8 at the Microgrid 2017 Conference for more information on engineering challenges in microgrid implementations!

Dan Jones is a project engineer; Doug Jones is a senior project engineer and department manager; and John Kumm is director, SCADA and Analytical Services at POWER Engineers. POWER Engineers is a global consulting and engineering firm specializing in the delivery of integrated solutions.

About the Author

Guest Post

gettyimages1341067688_sdl__1320x755

Revolutionizing Defense: The Crucial Role of Microgrids and Schneider Electric in Department of Defense Energy Resiliency

Sept. 13, 2024
Last month, the North American Electric Reliability Corporation (NERC) said that U.S. power grids are becoming more susceptible to cyberattacks every day, with vulnerable attack...

CumminsWP Cover_MG2021_2021-05-10_8-52-45

Transforming Microgrids with Hydrogen

Utilizing hydrogen in microgrids can play a key role in overcoming many of the challenges with the traditional energy economy such as aging infrastructure, changing customer demands...